What’s Happening in Nanaimo?

October brought another month of steady progress at Island Diesel Way in Nanaimo. Work continued across both buildings, with Building A moving forward with its concrete, mechanical, electrical, and exterior work, while Building B made progress on its wall panels and roof structure.

Here’s a look at what’s been happening on site throughout the month.

Building A

Building A continued to take shape as crews worked through several important stages of construction.

Mechanical and electrical rough-ins continued throughout October, alongside concrete work for the building’s dock levelers, stairs, and electrical room. Crews also worked on interior slab-on-grade preparation, including the installation of concrete reinforcement and vapour barriers.

Other work throughout the month included:

  • Concrete pours for interior slab areas and mezzanine preparations

  • Forming and pouring loading bay retaining walls

  • Continued wall cladding and flashing installation

  • Exterior painting of overhead doors and man doors

  • Installation of radon rock and associated pipework

  • Continued mechanical and electrical rough-ins

These activities are helping move Building A closer to its next stages of construction, with several interior and exterior components continuing to come together.

Building B

Building B also saw visible progress throughout October, particularly with its exterior structure and roof work.

Crews continued erecting the building’s wall panels, gradually bringing the building’s exterior enclosure into shape. As the month progressed, work also moved into building bolt-up and bracing, helping secure the structure.

By the end of October, crews had started placing the main roof’s Q-deck, marking another step forward in the building’s structural work.

General Site Work

Work also continued beyond the two buildings. Civil work around the site progressed, including preparations and coordination for upcoming work along the city street.

These activities are part of the ongoing site development and help prepare the property for the next phases of construction.

Looking Ahead

With October behind us, work is set to continue across both buildings. Upcoming activities include further mechanical and electrical work, the next stages of Building A’s main floor slab, and continued roof and structural work at Building B.

It’s been another productive month at Island Diesel Way, and we’re looking forward to seeing the project continue to take shape. We’ll keep sharing updates as construction progresses.